# Agency capacity planner

> Check agency capacity by role before accepting new client work. Account for time off, internal work and commitments, spot shortages and download a free CSV.

Canonical: https://workspace369.com/tools/agency-capacity-planner/
Last updated: 2026-10-10

[Free agency tools](https://workspace369.com/tools/)

Can your agency take on another project? Subtract time off, internal work and existing commitments from scheduled hours, then check the new work by role. Spare design hours cannot automatically cover a development shortage.

Updated October 10, 2026

No signupEditable sample numbersFree CSV download

## Your team, one planning period

Use the same week, month or quarter for every input. These example values are not industry benchmarks.

Role 1

Role name

Scheduled hoursLeave / holidaysInternal workCommitted client workProposed new work

Role 2

Role name

Scheduled hoursLeave / holidaysInternal workCommitted client workProposed new work

Calculations run in this page. Entered hours and role names are not submitted by this tool or stored after you leave. Download the CSV to keep your scenario.

## Check your inputs

Enter a non-negative number in every hours field. Values must be finite and no greater than 1,000,000.

Billable hours exceed available hours. Check the period, time off and any overtime before calculating.

Available hours must be greater than zero, and the target must be between 0% and 100%.

Leave and internal work cannot exceed scheduled hours for a role.

No result is shown until the inputs are valid. A blank field is not treated as zero.

## A role needs more capacity

## The hours fit this scenario

5h

Shortage across overloaded roles

Spare hours after proposed work

Design

-5 h left

Development

12 h left

Total net hours left: 7. Spare hours in one role do not erase a shortage in another. Check skills, individual availability and deadlines before committing.

Download prepared. Labels in the CSV are English.CSV includes your inputs, results and method. English labels.

## How do you calculate agency capacity?

For each role, start with scheduled working hours for the period. Deduct leave, holidays and the internal work you want to protect. That gives the hours available for client delivery. Deduct already committed client work and the proposed new project to find the remaining hours for that role.

Client capacity = scheduled hours − leave − internal work  
Remaining hours = client capacity − committed work − proposed work

Enter total hours across people in each role, rather than entering a headcount. Do not deduct internal work twice by also including it in committed client hours. A negative result shows a shortfall. The planner totals shortfalls separately from spare hours so an overall positive balance cannot hide a role bottleneck.

## A worked agency example

In the sample, Design has 80 scheduled hours, 8 hours off and 12 hours of internal work: 60 client-delivery hours. Existing work needs 45 hours and the proposed project needs 20, leaving a 5-hour shortage.

Development has 72 client-delivery hours and 60 hours of combined demand, leaving 12 spare hours. The total is positive by 7 hours, but the design work still does not fit. Reduce scope, move a deadline or confirm that a suitably skilled person can cover the work before promising delivery.

## What should you do with a capacity gap?

Review a shortfall with the people who will do the work. Split deliverables across dates, reduce optional scope or reassign work only when the required skills are available. A positive result is still a planning estimate: this tool does not model day-by-day scheduling, dependencies, skill levels, uncertainty or overlapping deadlines.

Use the [billable utilization calculator](https://workspace369.com/tools/billable-utilization-calculator/) to check the other side of the decision. Then review [agency profit-margin definitions and evidence](https://workspace369.com/research/agency-profit-margin-benchmarks/) and [agency pricing observations](https://workspace369.com/research/agency-pricing-benchmarks/) without treating them as a guaranteed result for your business.

## Keep the hours close to the project.

Workspace369 connects client records, projects, tasks and invoices. Time tracking and billable time come with every plan. Use those records to review actual work against the scenario you planned here.

This free tool is a standalone planning model. It does not connect to your workspace or claim that the app automatically calculates this exact report.

14-day free trial. Card required. After the trial: $74/month for Voyager. Renews automatically every month until you cancel. Cancel anytime in Settings → Billing.

[Explore agency management software →](https://workspace369.com/solutions/agency-management-software/)

[See current plans and limits.](https://workspace369.com/pricing/)

## Common questions

**Why can the team have spare hours and still be overloaded?**

Capacity is specific to skills and timing. A developer with spare time may not be able to complete a design task. This planner shows role shortages separately from spare hours; review individual skills and deadlines before treating hours as interchangeable.

**Should internal work be included in committed hours?**

Keep the categories separate. Put meetings, administration and protected internal work in the internal-work field. Put existing client-delivery commitments in committed client work. Counting the same hours in both fields understates your remaining capacity.

**Does this planner schedule individual tasks?**

No. It compares aggregate hours for a single period and up to 12 roles. It does not assign people to dates, model dependencies or predict completion. Use the result as a starting point for a detailed project schedule.

## Method and sources

Created by the Workspace369 editorial team. Method reviewed October 10, 2026. These are transparent calculations on your inputs, not survey findings or measured industry averages. Sources explain the concepts; our examples and implementation are original.

- [Productive: calculating resource capacity](https://productive.io/blog/how-to-calculate-resource-capacity/) — explains schedules, time off and role availability.
- [Teamwork: using the workload planner](https://support.teamwork.com/projects/workload/using-the-workload-planner) — distinguishes availability, assigned effort and capacity.