Client Change Request Template: Scope, Cost and Approval

Use this client change request template to document scope, cost, deadlines and approval. Includes a worked agency example and a practical Workspace369 workflow.

Updated September 13, 2026 · 6 min read

An approved client change request is attached to the original scope folder with a teal tab, a check-mark seal, and a small schedule card.
What's inside?What counts as a client change request?Copy this client change request templateTurn vague feedback into a request someone can assessWorked example: adding social cutdowns to a video projectMove the request through five clear decisionsKeep change records connected in Workspace369Check the record before work starts

A client change request template records a proposed change to agreed work, its effect on cost and timing, and the client's decision before delivery begins. For agencies, consultants and other service teams, it creates a traceable link between the original scope, the new request and the work eventually billed.

The practical test is simple: could a teammate understand what changed and why without searching an email chain? If not, the request needs a clearer record. This guide includes a copyable template, a worked example and a way to manage the record in Workspace369.

What counts as a client change request?

A change request proposes a departure from the agreed project baseline. The Association for Project Management describes change control as capturing and evaluating proposed baseline changes before approving, rejecting or deferring them. Its guidance also calls for assessing effects such as scope, quality, time, resources, cost and risk. Read APM's explanation of change control.

For client work, compare the request with the accepted proposal, deliverables and revision allowance. A spelling correction, an additional landing page and a new launch date need different decisions.

Client requestFirst classificationWhat to check
Correct a name that was supplied correctly in the briefCorrectionDoes the work fail an agreed requirement?
Refine a layout within an included review roundIncluded revisionDoes it fit the agreed revision allowance?
Add another page, format or audiencePotential scope changeWhat new work and review effort does it create?
Move delivery forwardSchedule changeCan capacity and dependencies support it?
Replace one deliverable with anotherScope trade-offWhat is removed, and what replaces it?

These categories are a working framework; the accepted engagement terms determine the actual boundary. For the broader delivery setup, see agency project management in Workspace369.

Copy this client change request template

Also readAgency project management software

Keep one record for each decision. Combine related requests only when they can be assessed and approved together.

FieldWhat to enter
Request ID and versionA unique reference, such as CR-014, version 1
Client and projectThe account and engagement affected
Requested by and dateThe person asking and when the request arrived
Current scope referenceAccepted proposal, section, deliverable and version
Requested changeWhat is added, removed or changed
Reason and intended outcomeThe problem the change should solve
Deliverables affectedFiles, formats, milestones or services involved
Acceptance criteriaObservable conditions for completing the change
Cost impactAdded fee, credit, scope exchange or no price change
Schedule and capacity impactRevised dates, dependencies and assigned effort
Assumptions and exclusionsInputs required and work still outside scope
OptionsApprove, decline, defer or choose a smaller alternative
Decision owner and deadlineWho can approve and when a decision is needed
Decision evidenceWritten response, decision date and approved version
Delivery and billing referencesTasks, files, proposal and invoice references

Store links to relevant records rather than copying confidential files into every document. If the change is too uncertain to price, record the discovery work needed before offering a delivery commitment.

Two colleagues review an additional project page and approved change request beside the original scope folder, a calendar, and coins.

Turn vague feedback into a request someone can assess

“Make this more engaging” does not identify an acceptance condition. “Add a customer example to the onboarding video after the pricing section” gives the team something concrete to evaluate.

For video work, Mark Studios' guide to actionable video revision notes recommends locating the exact moment, describing the observation and explaining why it matters. It also distinguishes corrections from changed requirements. Apply that feedback discipline to the request record, then assess the commercial impact separately.

For a website, use a page URL and screenshot. For a report, use a section and version. Ask the requester to describe the outcome before prescribing the implementation. A precise location and clear purpose help the delivery lead identify whether the request fits the existing scope.

Worked example: adding social cutdowns to a video project

The following is an illustrative planning example, not customer data or a recommended market rate.

A client approved one 90-second product video. During review, they ask for three additional 15-second vertical cutdowns. The original proposal does not include those exports or the reframing work.

Request fieldExample entry
ReferenceCR-014, version 1; proposal P-042, deliverables section
ChangeAdd three vertical cutdowns using the approved source footage
AcceptanceThree 15-second files in the agreed vertical format, with supplied captions and approved closing card
Added fee$600, assumed for this example
TimingTwo additional working days after complete client inputs and approval
Required inputsFinal captions, closing card and priority scenes
ExclusionsNew filming, new voiceover and additional languages
AlternativeDeliver the original video on schedule and defer the cutdowns
DecisionClient approver chooses an option against version 1

The delivery lead checks capacity before confirming the revised date. If the client changes the closing card after approval, the team compares that request with the accepted change record rather than reopening the entire original brief.

The key distinction is between a proposed change and an accepted commitment. Until the decision is recorded, keep the additional work separate from the approved delivery plan.

Move the request through five clear decisions

  1. Capture it. Record the client's wording, the source message and the current scope reference.
  2. Assess it. Identify effort, dependencies, price, timing and any simpler alternative.
  3. Present the options. Show the client what changes under each choice, including what happens if the request is deferred.
  4. Record the decision. Attach the written response to the specific request version. A meeting discussion still needs a durable decision record.
  5. Update delivery and billing. Adjust the relevant tasks, dates and commercial documents, then notify the people doing the work.

Use operational labels such as proposed, under assessment, awaiting decision, approved, declined and delivered wherever your team tracks status. An overdue decision is a blocker to resolve; it is not approval by silence.

A project lead hands off an approved client change folder linked to a delivery checklist, calendar, and billing document.

Keep change records connected in Workspace369

Workspace369's projects and tasks and client records provide places to connect the request to the engagement. Its proposals and invoice tools handle the commercial documents. This template is a process you can implement with those tools; it does not depend on a dedicated change-control module.

Start with a note or file containing the change record. Link it from the project and retain the source conversation with the client context. Once the client decides, create or update the delivery tasks and attach the relevant proposal or billing reference. Keep the approved version available when producing the next invoice.

Use your normal written approval process for the decision itself. Check the current product documentation and plan comparison for the tools available to your team.

Check the record before work starts

Before assigning the added work, confirm that another teammate can answer four questions: what changed, who approved it, which deadline applies and how it will be billed. If one answer is missing, close that gap before the request becomes a delivery task.

Use this client change request template on the next real request. Keep the record as short as the decision allows, but preserve the approved scope, version and evidence. That is what makes the later project handoff and invoice understandable.

Editorial note: Prepared with AI-assisted drafting and source verification on September 13, 2026. The worked example is fictional. Product references describe a suggested workflow using documented Workspace369 capabilities.

FAQ

What should a client change request include?

Include the client and project, request ID, current scope reference, requested change, reason, affected deliverables, cost and schedule impact, assumptions, decision owner, and written decision. Link the request to a specific document version so the team can tell exactly what the client approved before work begins.

Is every client revision a scope change?

No. A correction that brings work into line with the agreed requirements is different from a new deliverable or changed requirement. Compare the request with the accepted scope and revision allowance. If the boundary is unclear, clarify it with the client before treating the work as an extra charge.

Can a change request have no extra cost?

Yes. A team may absorb a small change or exchange one deliverable for another. Still record the decision, any deadline effect, and what has been removed or added. A zero-cost change can affect capacity, dependencies, or later approval even when the invoice total stays the same.